Programme
Dates, dependencies and milestones.
Requirement reference · Commercial 2.1 to 2.4Selection in the week commencing 12 October and an early instruction from the week commencing 19 October provide five weeks to complete Stage 5 design, the fire strategy, Building Regulations information and Licence to Alter support before possession.
Approvals before possession
Design and statutory approvals run in pre-construction, with the fire strategy informing the solution from the outset.
Long leads ordered early
Partitions, screens, VRF plant, gas monitoring, access control and FF&E are placed from the week commencing 19 October.
MEP drives the sequence
Containment and ductwork follow partition framing floor by floor, while commissioning starts three weeks before completion.
Possession: Mon 23 November 2026 · 13 weeks on site · Practical Completion: Fri 5 March 2027
Programme assumptions and clarifications
View assumptions
- Selection w/c 12 October 2026 and early instruction from w/c 19 October 2026.
- Date of Possession Monday 23 November 2026.
- Practical Completion Friday 5 March 2027, three weeks ahead of the client’s end-of-March target.
- Christmas shutdown from Thursday 24 December 2026 to Friday 1 January 2027 inclusive.
- Working hours Monday to Friday, 08:00 to 18:00.
- Electricity and water taken from existing mains and metered at possession and completion.
- Base build handed over complete, clean and with live services isolated and recorded.
- Landlord consent and Licence to Alter secured to suit the pre-construction programme, with OP support.
- No cranage or external scaffold required.
- FF&E as scheduled in the Contract Sum Analysis, with changes after design freeze controlled.